Contractor crews working on the I-5 – SR 16 Realignment – HOV Structure and Connections project have a series of overnight closures scheduled for the northbound Interstate 5 Exit 132 to westbound State Route 16 starting Monday, March 20. The closure is necessary so crews can install drainage crossings. Drivers will follow a signed detour. Closure hours are:

  • Monday, March 20 through Thursday, March 23: 11 p.m. until 4 a.m. each following day.
  • Friday, March 24: 11:59 p.m. until 5 a.m.
  • Saturday, March 25: 11:59 p.m. until 8 a.m.

Lane closures include two nights where southbound I-5 will be reduced to a single lane between Fife and Tacoma. Drivers are advised to plan extra time into their overnight travels.

  • Southbound I-5 will be reduced to a single lane between 54th Street in Fife to Bay Street in Tacoma during overnight hours on Saturday, March 18 and Thursday, March 23. Lane closures will begin on Saturday night at 10 p.m. with all lanes reopened by 10 a.m. Sunday, March 19. On Thursday, lane closures will begin at 9 p.m. with all lanes reopened by 4 a.m. Friday, March 24.
  • All lanes of northbound I-5 will be detoured to the collector/distributor lanes at Exit 133 from 11:59 p.m. until 4 a.m. the following day during the overnight hours of Tuesday, March 21 or Wednesday, March 22.
  • Additional weeknight single- and double-lane closures on I-5 are scheduled between Port of Tacoma Road and L Street. 

Ramp closures
In all instances where a ramp is closed, a signed detour will be in place.

Sunday, March 19

  • Southbound State Route 167 on-ramp to northbound I-5 will close from 9 p.m. to 4 a.m. the following day.
  • East 28th Street on-ramp to northbound I-5 will close from 11 p.m. to 4 a.m. the following day.

Monday, March 20

  • Southbound Interstate 705 ramp to northbound I-5 and southbound State Route 7 will close from 11 p.m. to 4 a.m. the following day.
  • East 28th Street on-ramp to northbound I-5 will close from 11 p.m. to 4 a.m. the following day.
  • Northbound I-5 exit to 20th Street East will close from 11 p.m. to 4 a.m. the following day.
  • Southbound SR 167 on-ramp to northbound I-5 will close from 9 p.m. to 4 a.m. the following day.

Tuesday, March 21

  • Southbound I-705 ramp to northbound I-5 and southbound SR 7 will close from 11 p.m. to 4 a.m. the following day.
  • Northbound I-5 exit to 20th Street East will close from 11 p.m. to 4 a.m. the following day.
  • East 28th Street on-ramp to northbound I-5 will close from 11 p.m. to 4 a.m. the following day.

Wednesday, March 22

  • Southbound SR 167 on-ramp to northbound I-5 will close from 9 p.m. to 4 a.m. the following day.
  • East 28th Street on-ramp to northbound I-5 will close from 11 p.m. to 4 a.m. the following day.

Thursday, March 23

  • Bay Street ramp to northbound SR 167 will close from 10 p.m. to 4 a.m. the following day. This work is weather dependent.
  • East 28th Street on-ramp to northbound I-5 will close from 11 p.m. to 4 a.m. the following day.
  • Southbound I-705 ramp to northbound I-5 and southbound SR 7 will close from 11:59 p.m. to 4 a.m. the following day.
  • Northbound I-5 exit to Portland Avenue will close from 11:59 p.m. to 4 a.m. the following day.

Friday, March 24

  • East 28th Street on-ramp to northbound I-5 will close from 11 p.m. to 4 a.m. the following day.


Northbound SR 7 ramp to northbound I-5 closed for construction

NB SR 7 ramp to NB I5

The month-long closure of the northbound SR 7 to northbound Interstate 5 is now underway. During the closure, crews are removing the existing SR 7 ramp to northbound I-5. Once the old ramp is gone, crews will reconstruct a new realigned ramp that will join a newly widened I-5. Weather permitting, the around the clock closure is expected to last through the month of March.

During the closure, drivers will be detoured from 38th Street using Interstate 705 and State Route 509 back to northbound I-5. Drivers are encouraged to plan extra time into their commute.

Special note
During this month-long closure, eastbound SR16 drivers using SR 7 as a detour will not be able to return to northbound I-5 via northbound SR 7.

Opening of new northbound I-5 ramp to SR 167 delayed due to weather. 

  • Rain and snow has again delayed the opening of the new northbound I-5 ramp to northbound State Route 167. If the forecast allows, the work, which involves closing the existing northbound I-5 exit to northbound SR 167 for an entire weekend, will be rescheduled for 10 p.m. Friday, March 24 through 4 a.m. Monday, March 27.

HOV makeover in Tacoma requires squeeze at SR 16/I-5 connection
Eastbound SR 16 drivers near I-5 can expect delays, congestion through spring 2017

Crews are building a new path for northbound I-5 in Tacoma Temporary changes are underway for drivers who use the eastbound SR 16 on-ramp to northbound I-5 in Tacoma. The change will allow crews to continue efforts to extend HOV lanes into Tacoma, but a similar configuration in 2015 created routine backups on SR 16 approaching I-5.

The eastbound SR 16 on-ramp to northbound I-5 is reduced to one lane through spring 2017.

The work zone space created by reducing eastbound SR 16 to one lane at northbound I-5 will allow crews to build new road approaches to the newly constructed bridge over Interstate 705/State Route 7. That new bridge will eventually carry all northbound I-5 traffic, and existing northbound I-5 lanes will be converted to HOV lanes.

Eastbound SR 16 travelers merging onto northbound I-5 can expect congestion and delays, particularly during the morning and afternoon commute hours.

McKinley Way overpass being rebuilt

  • East McKinley Way at I-5 in Tacoma closed to all traffic so crews can rebuild the overpass to accommodate a wider I-5. The roadway isn't expected to reopen to traffic until late winter 2018.  Until the overpass is rebuilt, drivers, bicyclists and pedestrians will detour to the rebuilt Pacific Avenue overpass. Rebuilding both overpasses is part of the effort to expand I-5 HOV lanes into Tacoma. 

 