Press

Press Room

Below are resources for members of the media seeking information or interviews about the Alaskan Way Viaduct Replacement Program.

Latest program news

  • Sept. 14 project update: Photos of progress inside the tunnel

    Many different elements of work must be completed before the SR 99 tunnel is ready for traffic. A previous program spotlight went into these areas of activity in detail. The linear distances of completed work are tracked on the progress tracker, which we are updating monthly (look for an update to the numbers soon). 

    But numbers only tell part of the story. This photo slideshow takes you inside the tunnel to see the recent progress being made beneath downtown Seattle.

    Drivers on the viaduct may have caught a glimpse of the recent transformation of the launch pit where Bertha began her journey (see the final photo in the slideshow). This summer, crews working for Seattle Tunnel Partners have been busy transforming the pit into the section of tunnel that will connect the bored tunnel to the SR 99 roadway near the stadiums. We will go more in-depth on this pivotal section of the tunnel in a future program spotlight.

    — more —

    Order: 1.3

  • Goodbye Bertha: Final piece of the tunneling machine removed from tunnel

    Disassembly of the world’s largest tunneling machine is now complete. This morning crews lifted the final pieces of the 8,000-ton giant out of the SR 99 tunnel’s disassembly pit near Seattle Center. The lift ended more than four months of difficult work, captured in this time-lapse video:

    Bertha broke through into the disassembly pit on April 4, 2017, and shortly thereafter built the tunnel’s final ring. Though the machine’s tunneling and ring-building work was complete, crews couldn’t complete roadway construction at the north portal until it was removed. Crews from the contractor Seattle Tunnel Partners have been working around the clock, disassembling the machine to make room for the roadway coming up through the tunnel behind it.

    It was tricky, tough, and impressive work, re-positioning the machine and dismantling its 8,000 tons of steel into pieces small enough to lift by crane or pull back out of the south end of the tunnel. The largest lift (or “pick” as crews call it) was 70 tons. Larger pieces required additional cutting on the surface before hauling. Hitachi Zosen, the machine’s manufacturer, will decide what to do with many of Bertha’s components. However, her signature 57-and-a-half-foot steel cutterhead was unique to this project and was cut up and trucked to a local steel recycler. Hitachi Zosen donated pieces of the cutterhead to the Port of Seattle and donated cutting tools and the control panel to Seattle’s Museum of History and Industry.

    What happens next

    Even while Bertha was still tunneling, crews were building the roadway inside the tunnel and working on electrical and other systems. With the machine completely gone, that work can continue uninterrupted along the 9,270-foot tunnel Bertha dug beneath Seattle. You can follow the work on a new progress tracker page.

    WSDOT’s focus is on finishing the tunnel for an estimated early 2019 opening, along with preparing for the Alaskan Way Viaduct’s demolition, the decommissioning of the Battery Street Tunnel, and improving surface street connections at the tunnel’s north and south ends. With disassembly complete, we are retiring the Follow Bertha webpage and updating the program Twitter account. But we will keep the same Twitter handle, @BerthaDigsSR99, because although the machine is gone, the product of her labors remains.

    The final piece of the tunneling machine being lifted out of the tunnel

    The final lift out of the disassembly pit, Aug. 23, 2017.

    — more —

    Order: 1.4

  • Coming soon: Alaskan Way Viaduct demolition open houses

    Demolition of the viaduct now in sight
     

    With tunnel boring complete, we’re deep in the planning stages for demolition of Seattle’s Alaskan Way Viaduct. On Thursday, we’ll launch an online open house to show what’s ahead and give the public a chance to comment on the work to come.

    Removing the seismically vulnerable viaduct will be the most visible change to Seattle’s waterfront in decades. The demolition work begins after the new State Route 99 tunnel opens, which is estimated for early 2019.

    WSDOT has successfully completed this type of work before. In 2011, we demolished the viaduct’s southern mile and built a new road in its place.  However, the remaining section of the viaduct is more challenging, as it is much closer to buildings, businesses, homes and the busy Colman Dock ferry terminal.

    Demolition is expected to take up to nine months, with the viaduct being demolished in sections to minimize localized disruptions. This contract will also involve other project elements, like filling in the Battery Street Tunnel and reconnecting several surface streets across Aurora Avenue North, which will take additional time.

    Several weeks before the new tunnel opens, WSDOT will shift Alaskan Way to the west of the viaduct, which will allow traffic to move along the waterfront before and during viaduct demolition. This new video below explains some of the planning for the demolition.

    Online open house

    The online open house will be live from August 3 - 14.

    In-person open house

    WSDOT is also hosting an in-person open house on August 10 for anyone interested in the work or who wants to speak with project staff. Representatives from Waterfront Seattle, Center City Connector Streetcar, Colman Dock, King County MetroOne Center City and Seattle Aquarium will also be available to answer questions.

    In-person open house details:

     

    WSDOT is committed to providing equal access to its facilities, programs and services for persons with disabilities. To request disability accommodations for the Aug. 10 open house event, email the ADA Office at least 7 days in advance at wsdotada@wsdot.wa.gov or call toll-free 1-855-362-4ADA (232). Persons who are deaf or hard of hearing may make a request by calling the Washington State Relay at 711.

    — more —
  • July 14 update: Bertha disassembly is halfway complete

    Seattle Tunnel Partners is now past the halfway point in disassembling the 8,000-ton tunneling machine Bertha. All of Bertha’s cutterhead is out of the disassembly pit and crews are working their way from top to bottom, cutting sections of the machine and lifting them by crane.

    Much of the machine’s trailing gear remains inside the tunnel, out of view of our time-lapse camera. Inside the tunnel, crews are cutting and hauling pieces of the trailing gear out of the tunnel via the south portal. This new time lapse video captures the work happening inside the tunnel.

    Work has progressed enough inside the disassembly pit to allow STP to use Bertha’s thrust rams to pull a large section of the trailing gear into the pit. Crews will now work from both outside and inside the tunnel to continue removing the trailing gear, which will help expedite work.

    Much of the conveyor system that moved extracted soils from the tunnel onto barges has also been removed. The photo below shows crews lifting the white over-water section of the conveyor last week.

    A crane removing a piece of the conveyor system

    While crews dismantle the machine, work continues on the road inside the tunnel. The photo below shows crews building the upper roadway inside the launch pit near the stadiums, where Bertha began her 9,270-foot tunneling journey underneath Seattle. You can monitor progress here.

    Concrete pours for the future roadway deck curing in the launch pit

    — more —

    Order: 1.5

  • June 15 project update: New time-lapse video shows tunneling machine disassembly

    The inner-workings of the SR 99 tunneling machine Bertha are now fully visible from the camera above the pit where disassembly continues. The upper shield that surrounded Bertha is now gone – lifted and hauled away. Only a small portion of the cutterhead spokes remain. Next, Seattle Tunnel Partners plans to remove work-deck platforms, hydraulic systems, hyperbaric equipment and ring-building equipment. Remember, there’s 8,000 tons of machinery inside the disassembly pit and inside the north end of the tunnel. This brief time-lapse video shows what seven weeks of nearly non-stop work looks like as workers continue dismantling the five-story-tall tunneling machine.

    — more —
  • June 9 project update: Disassembly continues and interior roadway progresses

    Seattle Tunnel Partners continues to work around the clock as they disassemble the SR 99 tunneling machine near Seattle Center. The face of the machine has dwindled in size as most of the cutterhead has been removed.

    Crews are also removing more pieces of the machine’s outer shield, exposing inner parts that weren’t previously visible from the pit. This includes the articulation jacks, which allowed the machine to change direction as it pushed beneath downtown Seattle.

    As work on the machine continues in the pit, disassembly is progressing from inside of the tunnel as well. STP is dismantling the trailing gear and disconnecting temporary utilities and ventilation that were necessary for the machine’s operations. These pieces are being removed through the south end of the tunnel. The below photos show disassembly progress, both in the disassembly pit and in the tunnel. Disassembly progress can also be tracked through the construction camera.

    Inside the tunnel, crews are hard at work on more than just removing the trailing gear. STP has now completed 66 percent of the southbound roadway and the corbels (wall foundations) are approaching the rear of the tunneling machine. The latest report tracking interior structures progress can be found in the information box on the Bertha page of our website.

    — more —

    Order: 1.8

Media requests

If you'd like to schedule an interview with a member of our team, please contact:

Laura Newborn
Media relations, Alaskan Way Viaduct Replacement Program 
206-805-2871
newborl@wsdot.wa.gov