• Project

US 395 - NSC Spokane River to Columbia - New Segment

On Monday, May 20, the southbound lanes of the North Spokane Corridor between Freya and Wellesley will close for the contractor to restripe the roadway.

On Tuesday, May 28, the contractor will close Wellesley Avenue between Market and Freya Street to complete the interchange work that was not finished prior to open the new section in 2023. The closure is anticipated to last one month and reopen June 28.

Project overview

This project will further expand the North Spokane Corridor south from its current end location at Columbia Avenue to the Spokane River. This includes the construction of a new interchange at Wellesley Avenue.

Timeline
April 2021 - August 2024
Project status
Construction
Funding
$49 Million
Project hotline

What to expect

Construction has started at Euclid Avenue where crews are in the process of building the North Spokane Corridor (NSC) overcrossing at Euclid Avenue. In addition, this project includes the construction of two new roundabouts at the north and southbound on/off-ramp interchange with Wellesley Avenue and the overcrossing structure for the NSC that will cross over Wellesley.

Wellesley Avenue is scheduled to reopen in November 2023. The new section of the North Spokane Corridor will also open new lanes at the same time from its current terminus at Freya/Francis south to Wellesley Avenue in November 2023 as well.

Map location for the future US 395/North Spokane Corridor construction between Columbia Avenue and the Spokane River. This includes the Wellesley interchange.