I-405 - SR 522 Vicinity to SR 527 Express Toll Lanes Improvement Project - Environmental Assessment

WSDOT and the Federal Highway Administration published the Environmental Assessment (EA) for the I-405, SR 522 Vicinity to SR 527 Express Toll Lanes Improvement Project on July 2, 2020. The comment period is open until August 6, 2020.

The State Environmental Protection Act (SEPA) Determination of Non-Significance (pdf 68.41 kb) for the Project was also published on July 2, 2020. Learn more about the EA and participate in our online public meeting from July 2 through August 6, 2020. 
 

Documents for download

How to submit comments

Send your comments through August 6, 2020 by using the following methods:

        WSDOT I-405/SR 167 Megaprogram
        Attn: Robert Woeck, I-405/SR 167 Megaprogram Environmental Engineering Manager
        600 108th Ave. NE, Suite 405
        Bellevue, WA 98004

Your feedback will be shared with WSDOT and FHWA and considered as project designs progress. We will publish responses to comments and questions in the final environmental decision document (expected in winter 2021).

What is an Environmental Assessment?

The Environmental Assessment describes the purpose and need of the project and provides to the public and decision makers about environmental effects and benefits of the project.

The EA compares future effects if WSDOT did or did not build the project and provides a detailed analysis of the proposed project’s effects.

What is the schedule for the environmental review?

  • Spring 2019: Scoping period
  • Spring 2019 through spring 2020: Development of Environmental Assessment
  • Summer 2020: Environmental Assessment released for public comment
  • Winter 2021: Final environmental documentation expected to be published with responses to comments received