US 195 - SR 271 to Plaza RD - Paving

Project news

A portion of US 195 traffic will be impacted during summer 2019. Roadway surface is rehabilitated from Rosalia to Plaza Rd using hot mix asphalt. The work will have potential short term traffic delays for roughly two months. The project was awarded to Shamrock Paving, Inc. on March 1, 2019.

Needs & benefits

The existing pavement surface for this 7.8 miles of US 195 has reached the end of its service life. The project will grind out the existing broken and rough surface, paving it back with a new hot mix asphalt which will maintain the serviceability of this route.

Timeline

Paving was completed July 26. Minor punchlist items remain.

View current construction and traffic impacts.

Funding

Financial Data for PIN 619506M
Funding Source Amount ($ in thousands)
2003 Gas Tax (Nickel Funding) $0
2005 Gas Tax (TPA) $0
Pre-Existing Funds (PEF) $3,870
CWA $0
Total $3,870

Contact

Mark Allen, project engineer
WSDOT Eastern Region
2714 N. Mayfair
Spokane, WA 99207
(509) 324-6232

Project map of paving on US 195 between SR 271 and Plaza Rd.