US 395 - North Spokane Corridor - Construction staging

Timeline of remaining North Spokane Corridor construction:

  1. Under construction: Columbia to Freya - Construction to be completed in 2020
  2. BNSF 2nd Railroad Realignment - Construction began Sept. 2019
  3. Spokane River to Columbia - Construction starts 2020
  4. Wellesley Ave. Improvements - Construction starts 2020
  5. Children of the Sun Trail - Construction starts 2020
  6. Sprague Ave. to Spokane River Phase 1 - Construction starts 2020
  7. Spokane River Crossing - Construction starts 2021
  8. Sprague Ave. to Spokane River Phase 2 - Construction starts 2023
  9. I-90 to Sprague Ave. - Construction starts 2022

North Spokane Corridor construction staging map to completion from Francis Ave. down to I-90/

Construction staging of the North Spokane Corridor to I-90.