US 395 - North Spokane Corridor - Quick facts

Background

  • The North Spokane Corridor (NSC) is a 10.5 mile limited access corridor, linking I-90 on the south, to existing US 2 and US 395 on the north.
  • Over 5.5 miles of the route is complete and open to traffic.

Environmental

  • Final Environmental Impact Statement (FEIS) was approved in April 1997.
  • An Environmental Impact Statement Reevaluation, for the section from I-90 to the Spokane River, was approved in May 2005.
  • Spokane River to Francis/Freya Interchange Environmental Reevaluation was approved in June 2012.
  • The environmental process included several hundred public meetings.
  • Additional environmental evaluation will be done as necessary as the project moves forward.

Financial - Funding to Date

  • Between 1990 and 2015 the NSC was allocated a total of $1.5 billion in funding - $140 million in Federal funds and $1.35 billion in State funds.
  • The North Spokane Corridor is now fully funded for construction to I-90. Estimated completion is 2029.
  • Funding totals include $45 million in Federal TIGER Grants and $879 million from the state Connecting Washington package. 
  • Completing the corridor, from Francis Ave. to I-90, is estimated to cost $879 million inflated to the years of expenditure. The remaining funds needed to complete the North Spokane Corridor was passed as part of the Connecting Washington package in 2015.
  • Connecting Washington construction projects began in 2018.
  • Design and right of way acquisition continues with WSDOT purchasing parcels as needed for construction.

Benefits & needs

  • Currently, there are only two north-south trade routes through Spokane. Both are on local arterials that run through neighborhoods, past shopping malls, schools, and parks.
  • Every year the US 395 corridor carries over 7.2 million tons of freight ($13.5 billion) through Spokane. Between 1993 and 2003, freight shipments on US 395 increased by 58%.
  • Improves safety by an estimated $22 million per year (2012 dollars) in avoided societal costs from collision reduction.
  • Reduces travel time by an estimated 9.4 million hours each year, with an annual dollar savings of approximately $240 million (2012 dollars).
  • Provides economic growth opportunities for adjacent commercial and industrial development with approximately 2,100 acres of appropriately zoned land along the route.
  • Supports alternative transportation options by providing park and ride lots, accommodating high capacity transit plans, and provides a multi-use trail (Children of the Sun Trail) along the facility.
  • Creates or supports an estimated ten jobs for each $1 million invested.

Progress

  • August 2001, "Ground-Breaking Ceremony", signaling the start of corridor construction.
  • In 2008, WSDOT applied practical design to lower the cost of the Spokane River to Francis Avenue section. This resulted in significantly reduced construction costs, while maintaining operational functionality, and allowing for staged construction.
  • On August 22, 2009, a "Ribbon Cutting Celebration" took place opening the first driveable section to traffic.
  • On October 2, 2012, a "Ribbon Cutting Celebration" was held, celebrating the completion of the northern 5.7 miles.
  • June 2015, the legislature funded NSC completion to I-90 as part of the Connecting Washington package.
  • BNSF Structures and Railway Realignment, using TIGER IV Grant Funds, completed Fall 2015.
  • Construction of a roundabout to improve the Wellesley/Freya intersection, completed Fall 2016.
  • A groundbreaking ceremony took place for the 2nd BNSF Railroad Realignment Project on September 27, 2019. Moving the BNSF tracks will allow for the construction and completion of the North Spokane Corridor to connect with I-90.

Finish what we started

  • Spring 2017, the NSC Freya St. Structures project began. Work was completed in late 2019.
  • Spring 2018, Columbia Ave. to Freya St. PCC Paving project. This project will be complete in the summer 2020.
  • September 29, 2019, the second BNSF railroad realignment project began.
  • 2020 construction season brings new projects to the North Spokane Corridor.
    • Paving from Columbia St. to the Spokane River.
    • A design-build project to construct the Children of the Sun Trail from its current location near Francis Ave. south and across the Spokane River.
    • Build an interchange at Wellesley Avenue
    • Construct new lanes of raised freeway from Ermina to Mission Ave. 
  • Final projects beyond 2020 include -
    • Spokane River crossing
    • Raised freeway from Mission Ave. south to Sprague Ave.
    • Sprague Ave. south to the I-90 connection.