US 97 - Boundary Bridge - Remove Fish Barrier

Project news

This project is moving toward winter suspension.  Traffic has been shifted from the bypass lane back to the roadway and the 12 ft. width restriction was lifted on Sept. 20, 2019.  Progress and traffic impacts will be updated weekly on the WSDOT North Central Region Construction Update and Travel Advisory when the project resumes in spring 2020.

Needs & benefits

The current culvert on Swauk Creek is a barrier to salmon and trout due to its size - a 6-foot by 9-foot oval – with a 4-foot drop from the outlet down to the creek bed. It is by the Swauk Creek Campground about 5 miles south of the Blewett Pass Summit (MP 159.67) In Kittitas County.

Replacing the culvert with a concrete bridge opens up valuable spawning and rearing habitat to steelhead, cutthroat, and rainbow trout, as well as providing safe passage under the highway for animals such as elk.

We’re working in partnership with the Mid-Columbia Fisheries Enhancement Group, for additional stream restoration work to improve floodplain connectivity, fish habitat and restore vegetation.

Timeline

Construction began April 15 building a bypass travel lane on a widened shoulder.  No full closures of the highway are planned. Expect a posted speed reduction through the work zone. Flaggers will be used to control traffic as needed - no more than 20 minute delays.  Some work might require limited overnight flagging, as well.

Funding

This project is funded through the WSDOT Capital Improvement Environmental Retrofit program (I-4) to remove fish barriers under state highways. A contract was awarded to Nisqually Construction Services, LLC on November 16, 2018 for $4,244,497.84.

Contact

Brian Pearson, Project Engineer 509-667-2880